 NLC TamilNadu Power Limited
NLCIL and TNEB/TANGEDCO desired to set up a 1000 MW coal based power project during 2001-02.

V.O.Chidambaranar Port Trust (VOCPT) [Formerly known as Tuticorin Port Trust] also agreed to allot area adjacent to Thoothukudi Thermal Power Station [TTPS] for setting up this project.

Ministry of Coal and Ministry of Power gave clearance for the project in Feb 2003.

Government of Tamil Nadu issued their consent for establishment of the project in 2003.

Government of India sanctioned the Tuticorin Thermal Power Project on 12.05.2008.

Read more  Read More ... Panoramic View of TTPP Administrative office - [Click to Enlarge]
 Vision & Mission
  Vision
To strive for operational excellence in power generation and to emerge as an environmental friendly and socially responsible leading power company

  Mission
    i. To strive towards greater cost competitiveness and work towards continued financial strength;
    ii. To continually imbibe best practices from the best Indian and International Organizations engaged in power generation;
    iii. To play an active role in society and be sensitive to emerging environmental issues.

  NTPL-ISO Certified Company
    Quality Management System
    (QMS) - ISO 9001:2015
    Environment Management System
    (EMS) - ISO 14001:2015
    Occupational Health and Safety Management System
    (OH&S) - ISO 45001:2018
    Energy Management System
    (EnMS) - ISO 50001:2011






For NLCIL Registered e-Procurement Vendors seeking Registration with NTPL eProcurement Click here
 Download Links
eProcurement Right to Information [RTI]

NTPL eProcurement Users Guideline
NTPL eProcurement forms downloads
RTI
PRODUCTION PERFORMANCE 2019-20
PARTICULARS UNIT VALUE
Gross Generation(GG) MU 4844.400
Gross Power Surrender MU 2067.000
GG including Gross Power Surrender MU 6911.400
Plant Load Factor(PLF) % 55.15
PLF including Gross Power Surrender % 78.68
Plant Availability Factor(PAF) % 78.157
Forced Outage(FO) % 18.12
Planned Outage(FO) % 2.92
Auxiliary Power Consumption (APC) % 7.172
Specific Oil Consumption (SOC) ml/kWh 0.462
Specific DM Water Consumption litre/kWh 0.469
HIGHLIGHTS 2019-20

Achieved Gross Generation of 6911.400 MU(78.68%) including Gross Power Surrender of 2067 MU

Ever highest PAF for any month since inception is 100.825(Mar-2020)

Ever lowest Specific DM Water Consumption for any year is 0.049 Lit/kWh

Ever lowest Specific Oil Consumption for any year is 0.462 ml/kWh

Ever Lowest Boiler Tube Leakage (BTL) for any year is 0.89%

100% Fly Ash utilization

NTPL started trading Un-requisitioned Surplus(URS)/Regulated power in the Day Ahead Market (DAM) to
increase Revenue from Operation through the Power Trading Department of NLC India Limited by
registering as a client to NLCIL

 EVENTS

Commercial Operation declaraion of Unit-1 completed on 18.06.2015 (photo gallery)
Commercial Operation declaraion of Unit-2 completed on 29.08.2015 (photo gallery)
Read more   Read More ...





Registered office:“Neyveli House”, No.135, EVR Periyar High Road,Kilpauk, Chennai - 600 010.
Copyright © 2012 NLC TamilNadu Power Limited All rights reserved. Best viewed in 1024x768 .